| Subject of Grant or Contract |
AL GHABAWI WASTEWATER TREATMENT PLANT PROJECT |
| Responsible Department |
NEAR - Directorate-General for Neighbourhood and Enlargement Negotiations |
| Programme Name |
6.0.111 - Neighbourhood, Development and International Cooperation Instrument - Global Europe (NDICI - Global Europe) |
| Type of Contract* |
- |
| Reference of the Legal Commitment (LC) |
SCR.LCM.439738.01 |
| Management Type |
Indirect management |
| Geographical Zone |
Jordan |
| Budget |
BGUE |
| Action Location |
Al-Ghabawi area East to Amman |
| Commitment Total Amount (EUR) (A+B) |
17,843,200.00 |
| Project end Date |
12/12/2027 |
| Commitment Contracted Amount (EUR) (A) |
17,843,200.00 |
| Benefiting Country |
Jordan 100% |
| Budget Line Name |
Southern neighbourhood |
| Funding Type |
Contribution agreement |
| Additional/Reduced Amount (EUR) (B) |
0.00 |
| Year |
2022 |
| Source of (Estimated) Detailed Amount |
The total commitment amount was attributed to a single beneficiary or in cases involving a consortium, it is possible that only the invoicing party is displayed, even if there are multiple beneficiaries who are all jointly and severally liable towards the EU for the performance of the underlying contract. |
| Reference (Budget) |
SCR.CTR.439738.01.2 |
| Commitment Consumed Amount (EUR) |
6,293,200.00 |
| Budget Line Number |
14 02 01 10 |
| Project Start Date |
13/12/2022 |
| Expense Type |
Operational |